Skip to content
April 19, 2022 - Media Release

Temporary single tracking coming to portion of Canada Line next week

Changes necessary to allow for next phase of Capstan Station construction

Rendering of the future Capstan Station

NEW WESTMINSTER, B.C. As construction of the new Capstan Station continues, service on a portion of the Canada Line will be temporarily adjusted to allow for crews to work safely. Starting April 26, there will be single tracking from Bridgeport to Richmond–Brighouse.

These changes will most impact customers travelling to and from Richmond–Brighouse, Aberdeen, and Lansdowne stations. Customers travelling between all other Canada Line stations may also notice a slight difference in travel times.

Reduced frequency scheduled between April 26 – June 5: 

Weeknight Impacts (April 26 – 29)

Stations

Extra wait time

Tuesday to Friday

Bridgeport to Richmond–Brighouse

7 minutes

6 p.m. to midnight

Weekend Impacts (April 30 – June 5)

Stations

Extra wait time

Saturdays

Sundays

Waterfront to

YVR–Airport

3 minutes

Beginning of service until 9 p.m.

Beginning of service until 7 p.m.

Bridgeport to Richmond–Brighouse

13 minutes

Beginning of service until 9 p.m.

Beginning of service until 7 p.m.

Additional bus service will be available for customers between Bridgeport Station and Richmond–Brighouse Station to meet capacity needs.

  • Buses will arrive approximately every 15 minutes on weeknights and up to every 10 minutes on weekends
  • Extra buses will stop at each Richmond branch station
  • Signage will be on site to assist customers
  • Customers are advised to build extra time in their commute.

We thank our customers for their patience while we continue the construction of Capstan Station. The station will provide better service for customers in the Capstan Village area of Richmond and remains on pace to open in 2023.

More information:
Capstan Station Webpage
Capstan Station renderings walkthrough video

Media contact:
TransLink Media Relations
E: media@translink.ca